IEEE Standard Conformance Test Procedures for Equipment Interconnecting Distributed Resources with Electric Power Systems
Published By | Publication Date | Number of Pages |
IEEE | 2005 | 63 |
New IEEE Standard – Active. This standard specifies the type, production, and commissioning tests that shall be performed to demonstrate that the interconnection functions and equipment of the distributed resources (DR) conform to IEEE Std 1547(TM). An interpretation is available at http://standards.ieee.org/findstds/interps/1547.1-2005.html
PDF Catalog
PDF Pages | PDF Title |
---|---|
2 | IEEE Standard Conformance Test Procedures for Equipment Interconnecting Distributed Resources with Electric Power Systems |
4 | Introduction |
5 | Notice to users Errata Interpretations Patents Participants |
8 | Contents |
10 | IEEE Standard Conformance Test Procedures for Equipment Interconnecting Distributed Resources with Electric Power Systems 1. Overview 1.1 Scope 1.2 Purpose |
11 | 1.3 Limitations 2. Normative references |
12 | 3. Definitions and acronyms 3.1 ICS boundaries 3.2 Definitions |
14 | 3.3 Acronyms 4. General requirements 4.1 Test result accuracy 4.2 Testing environment 4.3 Measurement accuracy and calibration of the testing equipment |
15 | 4.4 Product information 4.5 Test reports 4.6 Testing equipment requirements |
16 | 5. Type tests |
17 | 5.1 Temperature stability |
18 | 5.2 Test for response to abnormal voltage conditions |
22 | 5.3 Response to abnormal frequency conditions |
24 | 5.4 Synchronization |
32 | 5.5 Interconnection integrity |
33 | 5.6 Limitation of dc injection for inverters without interconnection transformers |
34 | 5.7 Unintentional islanding |
41 | 5.8 Reverse power (for unintentional islanding) |
42 | 5.9 Open phase |
43 | 5.10 Reconnect following abnormal condition disconnect |
44 | 5.11 Harmonics |
47 | 5.12 Flicker 6. Production tests |
48 | 6.1 Response to abnormal voltage 6.2 Response to abnormal frequency |
49 | 6.3 Synchronization |
50 | 6.4 Documentation 7. Commissioning test 7.1 General |
51 | 7.2 Verifications and inspections 7.3 Field-conducted type and production tests 7.4 Unintentional islanding functionality test |
52 | 7.5 Cease-to-energize functionality test |
53 | 7.6 Revised settings 8. Periodic interconnection tests |
54 | Annex A (normative) Test signals A.1 Magnitude test (ramp function)-general |
57 | A.2 Time test (step function)-general A.3 Reverse-power magnitude test (ramp function) |
59 | A.4 Reverse-power time test (step function) |
62 | Annex B (informative) Bibliography |